SUPREME COURT OF INDIA

Pioneer Urban Land & Infrastructure Ltd. v. Govindan Raghavan

Decision date:

02 April 2019 · Civil Appeal No. 12238 of 2018

Explain delayed possession, unfair buyer agreements and the refund claim in its factual context.

Read summaryRead court textOriginal PDF · 22 pages
Source and extraction notes

Official source

Draft summary

AI-assisted historical explanation. Independently checked against the source by an AI reviewer. Not reviewed by a lawyer. This historical summary does not certify the current legal position.

In one sentence

A buyer was entitled to refund after serious delay and could not be bound by unfair one-sided terms.

Question decided

Could the developer compel acceptance of substantially delayed possession?

Key holdings

Outcome

The developer’s appeals were dismissed and the consumer commission’s refund order affirmed.

Source PDF pages: 17, 18, 19, 20, 21, 22.

Plain-English explanation

The developer failed to obtain the occupancy certificate and offer possession within the agreed period or a reasonable time thereafter. By the time possession was offered, the buyer had faced substantial delay and financing costs. The Court did not treat signing the standard agreement as consent to every unfair term or as an obligation to accept the delayed flat indefinitely. It upheld the refund remedy and the particular interest treatment ordered by the consumer commission. This is the Govindan Raghavan consumer case, not the separate Pioneer Urban insolvency litigation. The practical point is that contractual form does not automatically defeat consumer protection. However, entitlement, interest and the effect of an offer of possession still depend on the agreement, chronology and governing law in each dispute.

Relevant law

Opinions

Two-judge bench; Justice Indu Malhotra authored the judgment.

Research notes and limits

Do not universalise the 10.7% rate. Check the 2019 consumer statute, RERA and later case law for current claims.

Judgment - source material

All pages of the downloaded court document follow, including separate opinions, annexures and any final joint order. This is machine-extracted original text, not an AI rewrite. Use the PDF to check exact wording.

Jump to a source page

Source PDF page 1

Open this page in the original PDF
1 
 
REPORTABLE 
 
IN THE SUPREME COURT OF INDIA 
CIVIL APPELLATE JURISDICTION 
 
CIVIL APPEAL NO. 12238 OF 2018 
 
Pioneer Urban Land & Infrastructure Ltd.            …Appellant 
 
Versus 
 
Govindan Raghavan                              …Respondent 
WITH 
 
CIVIL APPEAL NO. 1677 OF 2019 
 
Pioneer Urban Land & Infrastructure Ltd.            …Appellant 
 
Versus 
 
Geetu Gidwani Verma & Anr.                           …Respondent 
 
J U D G M E N T 
 
INDU MALHOTRA, J. 
 
1. The present statutory Appeals have been filed under Section 
23 of the Consumer Protection Act, 1986 to challenge the Final 
Judgment and Order dated 23.10.2018 passed in Consumer 

Source PDF page 2

Open this page in the original PDF
2 
 
Case No. 238 of 2017 and Consumer Case No. 239 of 2017 by 
the National Consume r Disputes Redressal Commission 
(hereinafter referred to as “the National Commission”). 
 
2. Since a common issue arises in both the Civil Appeals, they 
are being disposed of by the present common Judgment and 
Order. 
 
3. For the sake of brevity, the facts in C.A. No. 12238 of 2018 are 
being referred to, being the lead matter. 
The factual matrix of the said Civil Appeal is as under : 
3.1.    The Appellant – Builder launched a residential project 
by the name “Araya  Complex” in Sector 62, Golf Course 
Extension Road, Gurugram.  
   The Respondent – Flat Purchaser entered into a n 
Apartment Buyer’s Agreement dated 08.05.2012 with the 
Appellant – Builder to purchase an apartment in the said 
project for a total sale consideration of Rs. 4,83,25,280/-.  
   As per Clause 11.2 of the Agreement, the Appellant – 
Builder was to make all efforts to apply for the Occupancy 
Certificate within 39 months from the date of excavation, 
with a grace period of 180 days. 

Source PDF page 3

Open this page in the original PDF
3 
 
3.2.    The excavation of the project commenced on 
04.06.2012. As per Clause 11.2 of the Agreement, the 
Builder was required  to apply for the Occupancy 
Certificate by 04.09.2015, or within a further grace period 
of 6 months i.e. by 04.03.2016, and offer possession of the 
flat to the Respondent – Flat Purchaser. 
   The Appellant – Builder however failed to apply for the 
Occupancy Certificate as per the stipulations in  the 
Agreement. 
3.3.    The Respondent  – Flat Purchaser filed a Consumer 
Complaint before the National Commission on 27.01.2017 
alleging deficiency of service on the part of the Appellant – 
Builder for failure to obtain the Occupancy Certificate, 
and hand over possession of the flat.  
The Respondent prayed inter-alia for :- 
• Refund of the entire amount deposited being                
Rs. 4,48,43,026/-, along with Interest @18% p.a.; and 
• Compensation of Rs. 10,00,000/ - for mental agony, 
harassment, discomfort and undue hardship; and 

Source PDF page 4

Open this page in the original PDF
4 
 
• Refund of the wrongfully charged taxes including 
Service Tax, and other charges along with  Interest 
@18% p.a.; and 
• Litigation Costs of Rs. 1,00,000/-. 
3.4.    On 06.02.2017, the National Commission passed an ex-
parte Interim Order restraining the Appellant – Builder 
from cancelling the allotment made in favour of the 
Respondent – Flat Purchaser during the pendency of the 
Consumer Case. 
3.5.    During the pendency of the proceedings before the 
National Commission, t he Appellant – Builder obtained 
the Occupancy Certificate on 23.07.2018 , and issued a 
Possession Letter to the Respondent – Flat Purchaser on 
28.08.2018. 
3.6.    The Appellant – Builder submitted before the National 
Commission that since the construction of the apartment 
was complete , and the Occupancy Certificate had since 
been obtained, the Respondent – Flat Purchaser must be 
directed to take possession of the apartment, instead of 
directing refund of the amount deposited. 

Source PDF page 5

Open this page in the original PDF
5 
 
3.7.    The Respondent – Flat Purchaser  however submitted 
that he was not interested in taking possession of the 
apartment on account of the inordinate delay of almost 3 
years. The Respondent – Flat Purchaser stated that he 
had, in the meanwhile, taken an alternate property in 
Gurugram, and sought refund of the entire amount of Rs. 
4,48,43,026/- deposited by him along with Interest @18% 
p.a. 
3.8.    The National Commission vide Final Judgment and 
Order dated 23.10.2018 allowed the Consumer Complaint 
filed by the Respondent  – Flat Purchaser, and held that 
since the last date stipulated for construction had expired 
about 3 years before the Occupancy Certificate was 
obtained, the Respondent – Flat Purchaser could not be 
compelled to take possession at such a belated stage. 
   The grounds urged by the Appellant – Builder for delay 
in handing over possession were not justified, so as  to 
deny awarding compensation to the Respondent  – Flat 
Purchaser. The clauses in the Agreement were held to be 
wholly one  – sided, unfair, and not bind ing on  the 
Respondent – Flat Purchaser. 

Source PDF page 6

Open this page in the original PDF
6 
 
   The Appellant – Builder was directed to refund Rs. 
4,48,43,026/- i.e. the amount deposited by the 
Respondent – Flat Purchaser, along with Interest @10.7% 
S.I. p.a. towards compensation. The rate of Interest  
@10.7% S.I. p.a. was fixed in accordance with Rule 15 of 
the Haryana Real Estate (Regulation and Development) 
Rules, 2017 which reads as follows : 
“15. An allottee shall be compensated by the 
promoter for loss or damage sustained due to 
incorrect or false statement in the  notice, 
advertisement, prospectus or brochure in the 
terms of Section 12. In case, allottee wishes to 
withdraw from the project due to discontinuance 
of promoter’s business as developers on account 
of suspension or revocation of the registration or 
any ot her reason(s) in terms of clause (b) sub -
section (I) of Section 18 or the promoter fails to give 
possession of the apartment/ plot in accordance 
with terms and conditions of agreement for sale in 
terms of sub -section (4) of section 19. The 
promoter shall return the entire amount with 
interest as well as the compensation payable. The 
rate of interest payable by the promoter to the 
allottee or by the allottee to the promoter, as the 
case may be, shall be the State Bank of India 
highest marginal cost of  lending rate plus two 
percent. …” 
(emphasis supplied) 
 
   However, for the period when the Interim Order dated 
06.02.2017 was in operation, which restrained the 
Appellant – Builder from cancelling the Respondent’s  
allotment, no Interest was awarded. T he National 
Commission ordered payment of Interest from the date of 

Source PDF page 7

Open this page in the original PDF
7 
 
each installment till 05.02.2017; and from the date of the 
Order passed by the Commission till the date on which the 
amount would be refunded. 
3.9.    Aggrieved by the Order dated 23.10.2018 passed by the 
National Commission, the Appellant – Builder preferred 
the present statutory Appeal under Section 23 of the 
Consumer Protection Act, 1986. 
 
4. Mr. C.A. Sundaram, Senior Counsel appeared for the 
Appellant – Builder, and drew our attention to the following 
Clauses in the Apartment Buyer’s Agreement dated 
08.05.2012 viz. Clause 11.5 (ii), (iv) and (v) along with Clause 
20 which read as under : 
“11.5. (ii) In the event of further delay by the 
Developer in handing over of the possession of the 
Unit even after 12 months from the end of grace 
period, then in such case, the intending Allottee 
shall have an additional option to terminate this 
Agreement by giving termination notice of 90 days 
to the Developer and refund of the actu al 
installment paid by him against the Unit after 
adjusting the taxes paid  / interest / penalty on 
delayed payments.  
… 
(iv)    Developer shall, within ninety (90) days from 
the date of receipt of termination notice of said 
Unit, refund to the intending Allottee, all the 
monies received excluding the service tax 
collected on various remittances, till the date of 
the refund, from the Intending Allottee under this 
Agreement.  In case the Developer fails to refund 

Source PDF page 8

Open this page in the original PDF
8 
 
the Sale Price, the Developer shall pay interest to 
the Intending Allottee @ 9% per annum for any 
period beyond the said period of ninety (90) days.  
The Intending Allottee shall have no other claim 
against the Developer in respect of the said Unit  
along with the parking space.  The Intending 
Allottee in this event shall have no right to seek 
any compensation apart from the interest as 
stipulated herein. 
… 
(v) If the I ntending Allottee fails to exercise his 
right of termination within the time limit as 
aforesaid, by delivery to the Developer of a 
written notice acknowledged by the Developer in 
this regard, then he shall not be entitled to 
terminate this Agreement thereafter and he shall 
continue to be bound by the provisions of this 
Agreement, provided that in such case, the 
Developer shall continue to pay the compensation 
provided herein. 
 
20. RIGHT OF CANCELLATION BY THE 
ALLOTTEE 
Except to the extent specifically and e xpressly 
stated elsewhere in this Agreement, the Intending 
Allottee shall have the right to cancel this 
Agreement solely in the event of the clear and 
unambiguous failure of the warranties of the 
Developer that leads to frustration of the contract 
on that account.  In such case, the Allottee shall 
be entitled to a refund of the installments actually 
paid by it along  with interest thereon @ 6% per 
annum, within a period of 90 days from the date 
of communication to the Developer in this regard 
less any payments made towards taxes paid by 
the Developer or interest paid due or payable, any 
other amount of a non -refundable nature.  No 
other claim, whatsoever, monetary or otherwise 
shall lie against the Developer nor shall be raised 
otherwise or in any manner what soever by the 
Allottee.  Save and except to this limited extent, 
the Allottee shall not have any right to cancel this 
Agreement on any ground whatsoever.” 
(emphasis supplied) 
 
4.1.    It was submitted that the Respondent – Flat Purchaser 
was not entitled to refund of the amount deposited, since 

Source PDF page 9

Open this page in the original PDF
9 
 
the Apartment Buyer’s Agreement was not terminated by 
the Respondent – Flat Purchaser in accordance with 
Clause 11.5 (ii) of the Agreement, which stipulates that the 
allottee has to terminate the Ag reement by giving a 
Termination Notice of 90 days to the Developer. 
   Since t he Respondent – Flat Purchaser had not 
terminated the Agreement by a written notice as per 
Clause 11.5, the Builder could not sell the apartment, and 
refund the money to the Respondent – Flat Purchaser. On 
the contrary, the Respondent filed a Consumer Complaint 
and obtained an ex-parte Interim Order dated 06.02.2017 
restraining the Builder from cancelling the allotment made 
in favour of the Respondent. 
4.2.    It was  further submitted that if the filing of the 
Consumer Complaint is considered as an act of 
termination of the Agreement, then the same was pre -
mature. As per Clause 11.5 (ii), the Respondent – Flat 
Purchaser could have claimed refund only after the expiry 
of 12 months after the grace period came to an end i.e. 
after 04.03.2017. However, the Consumer Complaint was 
filed on 27.01.2017. In these circumstances, even if it is 

Source PDF page 10

Open this page in the original PDF
10 
 
found that the Appellant – Builder is liable to refund the 
amount deposited  with Interest, then  the date of the 
Impugned Order i.e. 23.10.2018, must be treated as the 
date of serving the Termination Notice as per Clause 11.5 
(ii) of the Agreement , and the Appellant – Builder should 
be held liable to pay Interest only after 90 days from the 
date of termination i.e. from 23.01.2019. 
4.3.    With respect to rate of Interest awarded by the National 
Commission, it was submitted that the Commission erred 
in granting Interest @10.7% S.I. p.a. even though Clause 
20 of the Agreement provided Interest @6% p.a. in case of 
delay in handing over possession. Even under Clause 11.5 
of the Agreement, the Builder was liable to pay Interest 
@9% p.a., but not @10.7%  S.I. p.a. The learned Senior 
Counsel relied upon this Court’s Judgment in Bharathi 
Knitting Company v. DHL Worldwide Express Courier 
Division of Airfreight Ltd.,1 and submitted that the National 
Commission could not have granted compensation in 
excess of the rate prescribed by the Agreement. 
 
                                                           
1 (1996) 4 SCC 704. 

Source PDF page 11

Open this page in the original PDF
11 
 
5. Mr. Sushil Kaushik, l earned Counsel represented the 
Respondent – Flat Purchaser. 
5.1.    It was submitted that the filing of the Consumer 
Complaint may be treated as his Termination Notice under 
Clause 11.5 (ii) of the Agreement. Under the Agreement, 
the Builder was obligated to apply for the Occupancy 
Certificate within 39 months from the date of excavation, 
with a grace period of further 6 months. The period got 
over by 04.03.3016 after taking into account the grace 
period. 
   Admittedly, the Appellant – Builder offered possession 
after an inordinate delay of almost 3 years on 28.08.2018. 
On account of the inordinate delay, the Respondent – Flat 
Purchaser had no option but to arrange for alternate 
accommodation in Gurugram. Hence, he could not be 
compelled to take possession of the apartment after such 
a long delay. 
  It was in these circumstances that the Respondent – Flat 
Purchaser sought stay of the cancellation of the allotment 
as a collateral, till his claim for refund was adjudicated by 
the National Commission. 

Source PDF page 12

Open this page in the original PDF
12 
 
5.2.    It was further submitted  that the Clauses of the 
Agreement were one -sided. As per Clause 6.4 (ii) of the 
Apartment Buyer’s Agreement, the Appellant Builder 
could charge Interest @18% p.a. for delayed payments. 
   However, the Appellant – Builder was not required to pay 
equivalent Interest to the Respondent – Flat Purchaser for 
delay in handing over possession of the flat. 
   On the contrary, as per Clause 11.5 (iv) of the 
Agreement, in case of delay on the part of the Appellant – 
Builder in handing over possession of the flat, the 
Respondent – Flat Purchaser was entitled to Interest @9% 
p.a. only. 
5.3.    The Respondent further submitted that the National 
Commission had ordered payment of Interest as per the 
statutory Rules i.e. Rule 15 of the Haryana Real Estate 
(Regulation and Development) Rules,  2017 @10.7% S.I. 
p.a. 
   The Respondent – Flat Purchaser submitted that he had 
obtained a loan for Rs. 3 ,30,00,000/- from Standard 
Chartered Bank to purchase the flat in question, and had 
entered into a Tripartite Loan Agreement with the Bank 

Source PDF page 13

Open this page in the original PDF
13 
 
and the Builder. The Respondent – Flat Purchaser had to 
pay Interest @10% p.a. for servicing the loan for the entire 
period. Hence, Interest @10.7% S.I. p.a. awarded by the 
National Commission was just and fair. 
   It was pointed out that even though the National 
Commission had not granted Interest for the period during 
which the Order of stay o f cancellation of the allotment  
was in operation, the Respondent – Flat Purchaser had to 
pay Interest to the Bank even for this period. 
5.4.    The Respondent – Flat Purchaser submitted  that the 
present Appeal be dismissed, and the Builder be directed 
to pay the amount a warded by the National Commission 
with Interest, within 1 week, so that the Respondent can 
discharge his loan liability. 
 
6. We have heard the  learned Counsel for both the parties, and 
perused the pleadings, and written submissions filed. 
6.1.    In the present case, admittedly the Appellant – Builder 
obtained the Occupancy Certificate almost 2 years after 
the date stipulated in the Apartment Buyer’s Agreement . 
As a consequence, there was a failure to hand over 

Source PDF page 14

Open this page in the original PDF
14 
 
possession of the flat to the Respondent – Flat Purchaser 
within a reasonable period. The Occupancy Certificate was 
obtained after a delay of more than 2 years on 28.08.2018 
during the pendency of the proceedings before the 
National Commission.  
   In Lucknow Development Authority v. M.K. Gupta,2 this 
Court held that w hen a person hires the services of a 
builder, or a contractor, for the construction of a house or 
a flat, and the same is for a consideration, it is a “service” 
as defined by Section 2 (o) of the Consumer Protection Act, 
1986. The inordinate delay in handing over possession of 
the flat clearly amounts to deficiency of service. 
   In Fortune Infrastructure & Anr. v. Trevor D’Lima & Ors.,3 
this Court held that a person cannot be made to wait 
indefinitely for possession of the flat allotted to him, and 
is entitled to seek refund of the amount paid by him, along 
with compensation. 
6.2.    The Respondent – Flat Purchaser has made out a clear 
case of deficiency of service on the part of the Appellant – 
Builder. The Respondent – Flat Purchaser was justified in 
                                                           
2 (1994) 1 SCC 243. 
3 (2018) 5 SCC 442. 

Source PDF page 15

Open this page in the original PDF
15 
 
terminating the Apartment Buyer’s Agreement by filing the 
Consumer Complaint, and cannot be compelled to accept 
the possession whenever it is offered by the Builder. The 
Respondent – Purchaser was legally entitled to seek refund 
of the money deposited by him a long with appropriate 
compensation. 
6.3.    The National Commission in the Impugned Order dated 
23.10.2018 held that the Clauses relied upon by the 
Builder were wholly one-sided, unfair and unreasonable, 
and could not be relied upon. 
   The Law Commission of India in its 199 th Report, 
addressed the issue of ‘Unfair (Procedural & Substantive) 
Terms in Contract ’. The Law Commission inter-alia 
recommended that a legislation be enacted to counter 
such unfair terms in contracts . In the draft legislati on 
provided in the Report, it was stated that : 
“A contract or a term thereof is substantively 
unfair if such contract or the term thereof is in 
itself harsh, oppressive or unconscionable to one 
of the parties.” 
 
6.4.     A perusal of the Apartment Buyer’s Agreement dated 
08.05.2012 reveals stark incongruities between the 
remedies available to both the parties. 

Source PDF page 16

Open this page in the original PDF
16 
 
   For instance, Clause 6.4 (ii) of the Agreement entitles the 
Appellant – Builder to charge Interest @18% p.a. on 
account of any delay in payment of installments from the 
Respondent – Flat Purchaser. 
   Clause 6.4 (iii) of the Agreement entitles the Appellant – 
Builder to cancel the allotment and terminate the 
Agreement, if any installment remains in arrears for more 
than 30 days. 
   On the other hand, as per Clause 11.5 of the Agreement, 
if the Appellant – Builder fails to deliver possession of the 
apartment within the stipulated period, the Respondent – 
Flat Purchaser has to wait for a period of 12 months after 
the end of the grace period, before serving a Termination 
Notice of 90 days on the Appellant – Builder, and even 
thereafter, the  Appellant – Builder gets 90 days to refund 
only the actual installment paid by the Respondent – Flat 
Purchaser, after adjusting the taxes paid , interest and 
penalty on delayed payments. In case of any delay 
thereafter, the Appellant – Builder is liable to pay Interest 
@9% p.a. only. 

Source PDF page 17

Open this page in the original PDF
17 
 
6.5.    Another instance is Clause 23.4 of the Agreement which 
entitles the Appellant – Builder to serve a Termination 
Notice upon the Respondent – Flat Purchaser for breach 
of any contractual obligation. If the Respondent – Flat 
Purchaser fails to rectify the default within 30 days of the 
Termination Notice, then th e Agreement automatically 
stands cancelled, and the Appellant – Builder has the right 
to forfeit the entire amount of Earnest Money towards 
liquidated damages. 
   On the other hand, as Clause 11.5 (v) of the Agreement, 
if the Respondent – Flat Purchaser fails to exercise his 
right of termination within the time limit provided in 
Clause 11.5, then he shall not be entitled to terminate the 
Agreement thereafter , and shall be bound by the 
provisions of the Agreement. 
6.6.    Section 2 (r) of the Consumer  Protection Act, 1986 
defines ‘unfair trade practices’ in the following words : 
“‘unfair trade practice’ means a trade practice which, for 
the purpose of promoting the sale, use or supply of any 
goods or for the provision of any service, adopts any unfair 
method or unfair or deceptive practice …”, and includes any 

Source PDF page 18

Open this page in the original PDF
18 
 
of the practices  enumerated therein . The provision is 
illustrative, and not exhaustive. 
   In Central Inland Water Transport Corporation Limited 
and Ors. v. Brojo Nath Ganguly and Ors.,4 this Court held 
that : 
 “89. … Our judges are bound by their oath to 
‘uphold the Constitution and the laws’. The 
Constitution was enacted to secure to all the 
citizens of this country social and economic 
justice. Article 14 of the Constitution guarantees 
to all persons equality before the law and equal 
protection of the laws. This principle is that the 
courts will not enforce and will, when called upon 
to do so, strike down an unfair and unreasonable 
contract, or an unfair and unreasonable clause in 
a contract, entered into between parties who are 
not equal in bargaining power. It is difficult to give 
an exhaustive list of all bargains of this type. No 
court can visualize the different situations which 
can arise in the affairs of men. One can only 
attempt to  give some illustrations. For instance, 
the above principle will apply where the 
inequality of bargaining power is the result of the 
great disparity in the economic strength of the 
contracting parties. It will apply where the 
inequality is the result of circumstances, whether 
of the creation of the parties or not. It will apply to 
situations in which the weaker party is in a 
position in which he can obtain goods or services 
or means of livelihood only upon the terms 
imposed by the stronger party or go without them. 
It will also apply where a man has no choice, or 
rather no meaningful choice, but to give his assent 
to a contract or to sign on the dotted line in a 
prescribed or standard form or to accept a set of 
rules as part of the contract, however unfair, 
unreasonable and unconscionable a clause in 
that contract or form or rules may be. This 
principle, however, will not apply where the 
bargaining power of the contracting parties is 
equal or almost equal. This principle may not 
                                                           
4 (1986) 3 SCC 156. 

Source PDF page 19

Open this page in the original PDF
19 
 
apply where both parties are b usinessmen and 
the contract is a commercial transaction. … 
… These cases can neither be enumerated nor 
fully illustrated. The court must judge each case 
on its own facts and circumstances.” 
(emphasis supplied) 
 
 
6.7.    A term of a contract will not be final and binding if it is 
shown that the flat purchasers had no option but to sign 
on the dotted line, on a contract framed by the builder. 
   The contractual terms of the Agreement dated 
08.05.2012 are ex-facie one-sided, unfair, and 
unreasonable. The i ncorporation of  such one -sided 
clauses in an agreement constitutes an unfair trade 
practice as per Section 2 (r) of the Consumer Protection 
Act, 1986 since it adopts unfair methods or practices for 
the purpose of selling the flats by the Builder. 
 
7. In view of the above discussion, we have no hesitation in 
holding that the terms of the Apartment Buyer’s Agreement 
dated 08.05.2012 were wholly one -sided and unfair to the 
Respondent – Flat Purchaser. The Appellant – Builder could 
not seek to bind the Res pondent with such  one-sided 
contractual terms. 
 

Source PDF page 20

Open this page in the original PDF
20 
 
8. We also reject the submission made by the Appellant – Builder 
that the National Commission was not justified in awarding 
Interest @10.7% S.I. p.a. for the period commencing from the 
date of payment of each installment, till the date on which the 
amount was paid, excluding only the period during which the 
stay of cancellation of the allotment was in operation. 
   In Bangalore Development Authority  v. Syndicate Bank,5 a 
Coordinate Bench of this Court held that when possession of 
the allotted plot/flat/house is not delivered within the 
specified time, the allottee is entitled to a refund of the amount 
paid, with reasonable Interest thereon from the date of 
payment till the date of refund. 
8.1.    In the present case, the National Commission has 
passed an equitable Order. The Commission has not 
awarded any Interest for the period during which the 
Order of stay o f cancellation of the allotment  was in 
operation on the request of  the Respondent – Flat 
Purchaser.  
   The National Commission has rightly awarded Interest 
@10.7% S.I. p.a. by applying Rule 15 of the Haryana Real 
                                                           
5 (2007) 6 SCC 711. 

Source PDF page 21

Open this page in the original PDF
21 
 
Estate (Regulation And  Development) Rules, 2017 from 
the date of each installment till 05.02.2017 i.e. till the date 
after which  the Order of stay of cancellation of the 
allotment was passed; and thereafter, from the date of the 
Commission’s final Order till the date on which t he 
amount is refunded with Interest. 
 
9. We see no illegality in the Impugned Order dated 23.10.2018 
passed by the National Commission. The Appellant – Builder 
failed to fulfill his contractual obligation  of obtaining the 
Occupancy Certificate and offering possession of the flat to the 
Respondent – Purchaser within the time stipulated in the 
Agreement, or within a reasonable time thereafter . The 
Respondent – Flat Purchaser could not be compelled to take 
possession of the flat, even though it was offered almost 2 
years after the grace period under the Agreement expired. 
During this period, the Respondent – Flat Purchaser had to 
service a loan that he had obtained for purchasing the flat, by 
paying Interest @ 10% to the Bank . In the meanwhile, the 
Respondent – Flat Purchaser also located an alternate 
property in Gurugram. In these circumstances, t he 

Source PDF page 22

Open this page in the original PDF
22 
 
Respondent – Flat Purchaser was entitled to be granted the 
relief prayed for i.e. refund of the entire amount dep osited by 
him with Interest. 
 
10. The Civil Appeals are accordingly dismissed, and the Final 
Judgment and Order dated 23.10.2018 passed by the National 
Consumer Disputes Redressal Commission is affirmed. The 
appellant is granted a period of three month s from today to 
refund the amount to the respondent.  All pending 
Applications, if any, are accordingly disposed of. 
 
 
 
.....................................J. 
(UDAY UMESH LALIT) 
 
 
 
 
.…...............………………J. 
(INDU MALHOTRA) 
 
 
New Delhi, 
April 2, 2019.