SUPREME COURT OF INDIA

Kailash Nath Associates v. Delhi Development Authority

Decision date:

09 January 2015 · Civil Appeal No. 193 of 2015

Explain reasonable compensation, loss and forfeiture under section 74 of the Contract Act.

Read summaryRead court textOriginal PDF · 41 pages
Source and extraction notes

Official source

Draft summary

AI-assisted historical explanation. Independently checked against the source by an AI reviewer. Not reviewed by a lawyer. This historical summary does not certify the current legal position.

In one sentence

Section 74 permits reasonable compensation, not a windfall through automatic forfeiture.

Question decided

When can a contractual sum or earnest money be retained for breach?

Key holdings

Outcome

The appeal was allowed and the Single Judge’s refund order restored.

Source PDF pages: 38, 39, 40, 41.

Plain-English explanation

A contract may specify a sum payable on breach, but that figure is not automatically an entitlement to keep money regardless of what happened. The Court explained the compensatory character of section 74 and the distinction between loss capable of proof and loss difficult to quantify. In the dispute before it, the authority had no established breach or loss supporting the forfeiture and had benefited from the later auction. The decision also distinguished contractual forfeiture from a public-auction situation before an agreement is reached. Readers should therefore avoid treating all deposits alike. The contract’s formation, terms, alleged breach and evidence of loss remain important. The judgment is useful for understanding reasonable compensation, but it is not a universal rule that earnest money must always be refunded.

Relevant law

Opinions

Two-judge bench; Justice R.F. Nariman authored the judgment.

Research notes and limits

Preserve the pre-contract public-auction distinction and the qualification for loss difficult to prove.

Judgment - source material

All pages of the downloaded court document follow, including separate opinions, annexures and any final joint order. This is machine-extracted original text, not an AI rewrite. Use the PDF to check exact wording.

Jump to a source page

Source PDF page 1

Open this page in the original PDF
Page  1
REPORTABLE
 
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 193 OF 2015
[ARISING OUT OF SLP (CIVIL) NO.32039 OF 2012]
M/s. Kailash Nath Associates                                         …Appellant 
Versus
 
Delhi Development Authority & Anr.                  ...Respondents
J U D G M E N T
R.F. Nariman, J.
1. Leave granted. 
2. The present appeal arises out of a public auction conducted by  
the  Delhi  Development  Authority  (“DDA”)  wherein  the  appellant  
made the highest bid for Plot No.2-A, Bhikaji Cama Place, District  
Centre,  New  Delhi  for  3.12  Crores  (Rupees  Three  Crores  Twelve 
Lakhs).  As per the terms and conditions of the auction, the appellant,  
being the highest bidder, deposited a sum of Rs.78,00,000/- (Rupees  
1

Source PDF page 2

Open this page in the original PDF
Page  2
Seventy Eight Lakhs), being 25% of the bid amount, with the DDA,  
this being earnest money under the terms of the conditions of auction.  
The relevant provisions in the conditions of auction read as follows:
“(ii) The highest bidder shall, at the fall of the hammer,  
pay  to  the  Delhi  Development  Authority  through  the  
officer conducting the auction, 25% of the bid amount as  
earnest money either in cash or by Bank Draft in favour  
of  the  Delhi  Development  Authority,  or  Cheque  
guaranteed by a Scheduled Bank as “good for payment  
for three months” in favour of the Delhi Development  
Authority. If the earnest money is not paid, the auction  
held in respect of that plot will be cancelled. 
(iii) The highest bid shall be subject to the acceptance of  
Vice-Chairman, DDA or such other officer(s) as may be  
authorized by him on his behalf. The highest bid may be  
rejected without assigning any reason. 
(iv) In case of default, breach or non-compliance of any  
of  the  terms  and  conditions  of  the  auction  or  mis  
-representation by the bidder and/or intending purchaser,  
the earnest money shall be forfeited. 
(v) The successful bidder shall submit a duly filled-in  
application in the form attached immediately after the  
close of the auction of plot in question. 
(vi) When the bid is accepted by the DDA, the intending  
purchaser shall be informed of such acceptance in writing 
and  the  intending  purchaser  shall,  within  3  months  
thereof,  pay  to  the  Delhi  Development  Authority,  the  
balance 75% amount of the bid, in cash or by Bank Draft  
in  favour  of  the  Delhi  Development  Authority  or  by  
Cheque guaranteed by a Scheduled Bank as “good for  
payment  for  three  months”  in  favour  of  the  Delhi  
Development Authority. If the bid is not accepted, the  
earnest  money  will  be  refunded  to  the  intending  
2

Source PDF page 3

Open this page in the original PDF
Page  3
purchaser without any interest unless the earnest money  
is forfeited under para 2 (iv) above.”
3. On  18.2.1982,  the  DDA  acknowledged  the  receipt  of  
Rs.78,00,000/-  (Rupees  Seventy  Eight  Lakhs),  accepted  the  
appellant’s bid and directed the appellant to deposit the remaining  
75% by 17.5.1982.  However, as there was a general recession in the  
industry,  the  appellant  and  persons  similarly  placed  made  
representations sometime in May, 1982 for extending the time for  
payment of the remaining amount.  The DDA set up a High Powered  
Committee  to look into these representations.   The High Powered  
Committee on 21.7.1982 recommended granting the extension of time  
to bidders for depositing the remaining amount of 75%.  Based on the  
High Powered Committee’s report, by a letter dated 11.8.1982, the  
DDA extended time for payment upto 28.10.1982 with varying rates  
of interest starting from 18% and going upto 36%.
4. Another High Powered Committee was also set up by the DDA  
in  order  to  find  out  whether  further  time  should  be  given  to  the  
appellant and persons similarly situate to the appellant. 
3

Source PDF page 4

Open this page in the original PDF
Page  4
5. The second High Powered Committee recommended that the  
time  for  payment  be  extended  and  specifically  mentioned  the  
appellant’s name as a person who should be given more time to pay  
the balance amount.  Despite the fact that on 14.5.1984 the DDA  
accepted  the  recommendations  of  the  second  High  Powered  
Committee, nothing happened till 1.12.1987.  Several letters had been  
written by the appellant to DDA from 1984 to 1987 but no answer was 
forthcoming by the DDA. 
6. Vide a letter dated 1.12.1987, which is an important letter on the 
basis of which the fate of this appeal largely depends, the DDA stated  
as follows:
“WITHOUT PREJUDICE’
DELHI DEVELOPMENT AUTHORITY 
VIKAS SADAN 
I.N.A.
New Delhi-23……198… . 
No.F.32(2)/82/Impl.-I/4 
From: DIRECTOR (C.L) 
DELHI DEVELOPMENT AUTHORITY 
To, 
M/s. Kailash Nath & Associates,
1006, Kanchanjanga Building, 
4

Source PDF page 5

Open this page in the original PDF
Page  5
18, Bara Khamba Road, 
New Delhi-110001. 
Sub: Regarding payment of balance premium in respect  
of Plot No.2-A situated in Bhikaji Cama Place 
          Distt. Centre. 
Sir, 
With  reference  to  the  above  subject,  I  am  directed  to 
inform you that your case for relaxing the provisions of  
Nazul Rules, 1981, to condone the delay for the payment  
of balance premium in installments was referred to the  
Govt. of India, Min. of Urban Development. Before the  
case is further examined by the Govt. of India, Min. of  
Urban  Development,  you  are  requested  to  give  your  
consent for making payment of balance amount of 75%  
premium within the period as may be fixed alongwith  
18% interest charges p.a. on the belated payment. Further  
the schedule of payment and conditions if any will be as  
per  the  directions  issued  by  the  Ministry  of  Urban  
Development, Govt. of India. It is, however, made clear  
that this letter does not carry any commitment.
Your consent should reach to this office within 3 days 
from the date of issue of this letter. 
Dated 1.12.87
Yours faithfully, 
Sd/
DIRECTOR (C.L)” 
7. The appellant replied to the said letter on the same day itself in  
the following terms:
“KAILASH NATH & ASSOCIATES 
5

Source PDF page 6

Open this page in the original PDF
Page  6
Tel.: 3312648, 3314269 
1006, KANCHENJUNGA, 
18, BARAKHAMBA ROAD, 
NEW DELHI-II0001 
Regd. Ack. Due. 
December 1, 1987. 
The Director (C.L.), 
Delhi Development Authority, 
Vikas Sadan, I.N.A., 
New Delhi-l 10023. 
Subject: Payment of balance premium in respect of 
plot No.2-A Bhikaji Cama Place Distt. 
Centre, New Delhi. 
Dear Sir, 
We are thankful to you for your letter No. F.30(2)/82-
Impl.- I/4 dated nil received by us this afternoon, on the 
above subject. 
We  hereby  give  our  consent  that  we  shall  make  the  
payment of the balance amount of 75% premium within  
the  period  as  may  be  fixed  as  per  the  schedule  of  
payment  and  conditions,  if  any  imposed,  as  per  the  
directions issued by the Ministry of Urban Development,  
Govt.  of  India,  alongwith  18%  interest  charges  per  
annum on the belated payment. 
We now request you to kindly convey us your formal  
approval to our making the said payment in installments  
as requested for. 
Thanking you, 
Yours faithfully 
For KAILASH NATH & ASSOCIATES, 
Sd/
6

Source PDF page 7

Open this page in the original PDF
Page  7
Partner
Advance copy sent through Special Messenger.”
8. The Central Government informed the DDA vide a letter dated  
1.3.1990 that the land auctioned to the appellant was not Nazul land  
and, therefore, the Central Government would have nothing further to  
do  with  the  matter.  Meanwhile,  the  appellant  filed  Writ  Petition  
No.2395 of 1990 in the Delhi High Court in which it claimed that  
persons similar to the appellant, namely, M/s. Ansal Properties and  
Industries Private Limited and M/s Skipper Tower Private Limited had 
been  allowed  to  pay  the  balance  75%  premium  and  were  in  fact  
allotted other plots.  Pleading Article 14, the appellant stated that they  
were entitled to the same treatment. 
9. By a judgment and order dated 2.9.1993, the Delhi High Court  
held that as the auction was held as per terms and conditions of the  
auction,  a  dispute  regarding  the  same  is  a  matter  of  contract  and 
cannot  be  gone  into  in  proceedings  under  Article  226  of  the  
Constitution.  It was further observed that on facts, the Court found no  
force in the contention raised on behalf of the appellant regarding  
discrimination.   An  SLP against  this order was also  dismissed  on  
16.12.1993  by  the  Supreme  Court  stating  that  the  appellant  is  at  
7

Source PDF page 8

Open this page in the original PDF
Page  8
liberty to take whatever steps are permitted to the appellant under law  
to challenge forfeiture of earnest money, which had been done by a  
letter  of  6.10.1993.   This  letter  is  also  important  for  the  correct  
determination of this appeal and is set out hereinbelow:-
“REGD.A.D. 
DELHI DEVELOPMENT AUTHORITY
VIKAS SADAN
I.N.A.
New Delhi-23,    6.10.1993 
No.F.32(2)/82/CL/3816 
From: DY . DIRECTOR (CL). 
To, 
M/s. Kailash Nath & Associates, 
1006, Kanchanjanga Building, 
18, Bara Khamba Road, 
New Delhi-l10001. 
Subject: Plot No.2-A in Bhikaji Cama Place Distt. Centre. 
Sir,
Consequent upon your failure to deposit the balance 75%  
premium of the aforesaid plot and dismissal of C.W.P. No. 
2395 of 1990 by the Hon’ble High Court, Delhi, I am  
directed to inform you that the bid/ allotment of the said  
plot in your favour has been cancelled and earnest money  
amounting to Rs.78,00,000/- deposited by you at the time  
of auction has been forfeited. 
Yours faithfully, 
8

Source PDF page 9

Open this page in the original PDF
Page  9
Sd/
(JAGDISH CHANDER) 
DEPUTY DIRECTOR (CL)”
10. The  appellant  then  filed  a  suit  for  specific  performance  on  
17.2.1994 and in the alternative for recovery of damages and recovery  
of  the  earnest  amount  of  Rs.78,00,000/-  (Rupees  Seventy  Eight  
Lakhs).  Shortly after the suit was filed, on 23.2.1994, the DDA re-
auctioned  the  premises  which  fetched  a  sum  of  Rs.11.78  Crores  
(Rupees Eleven Crores Seventy Eight Lakhs). 
11. The  learned  Single  Judge  by  a  judgment  and  order  dated  
10.9.2007 dismissed the appellant’s suit for specific performance and  
damages but ordered refund of the earnest money forfeited together  
with 9% per annum interest.  The learned Single Judge held:-
“65. Defendant No.1 instead of following the aforesaid  
course, found merit in the representations received not  
only from the plaintiff but such similar situated parties.  
It is in view thereof that the matter went as far as setting  
up of two committees to repeatedly examine the matter  
and to come to a conclusion.  The case of defendant no.1  
was that the material produced by the plaintiff and such  
similar persons gave rise to a cause to extend the time  
for  making  the  payment  subject  to  certain  terms  and  
conditions.   However,  in  view  of  the  perception  of  
defendant no.1 that the consent of UOI, defendant no.2,  
would be required, the land being Nazul land, the file  
was forwarded to defendant no.2.  The matter did not rest 
at this since thereafter UOI did grant such consent but  
9

Source PDF page 10

Open this page in the original PDF
Page  10
sent back the file of the plaintiff only on account of the  
fact that the land in question was not Nazul land. The net  
effect of this is that there was no permission required  
from the UOI and the decision taken by defendant no.1 to  
extend  the  time  period  for  making  the  payment,  thus,  
stood as it is. 
66. In my considered view, it is not open for defendant  
no.1 to state that while it recommended the case of other  
similarly situated parties in case of Nazul land to the  
Government  and  obtained  permission  for  grant  of  
extension of time, in case of non-Nazul land where such  
permission was not required, a different parameter was  
required to be followed.  It may be mentioned at the cost  
of  repetition  that  the  plaintiff  was  a  party  which  
volunteered  to  pay  interest  @18%  per  annum  unlike  
some  of  the  other  parties.   There  is  merit  in  the  
contention  of  learned  Counsel  for  the  plaintiff  that  
defendant no.1 after treating the contract as subsistent  
having  extended  time  for  making  the  payment  was  at  
least required to give a notice to the plaintiff to perform  
the agreement prior to terminating the agreement and  
could  not  straightaway  terminate  the  same.   This  
conclusion can draw strength from the observations in  
Halsbury Laws of England (supra) referred to aforesaid  
as also in Webb v. Hughes (supra).  It is clearly a case  
where there has been waiver of the time being essence of  
the  contract  by  conduct  of  the  parties  and,  thus,  
defendant no.1 was required to give notice on the day  
appointed for completion of the contract failing which  
only termination could take place. 
67. There were numerous communications exchanged  
between the parties.  The recommendations of the two  
high-powered committees constituted by defendant no.1  
made  its  recommendations  which  were  accepted  by  
defendant no.1 vide its resolution dated 14.5.1984 (Ex.  
DW2/P-4).   Having accepted the recommendations, in  
the case of the plaintiff defendant no.1 was required to  
do nothing further but mistakenly referred the case to  
10

Source PDF page 11

Open this page in the original PDF
Page  11
UOI  for its approval  assuming  the  case  to  be  one  of  
Nazul land.  Plaintiff sent repeated reminders vide letters  
dated 9-12-1985 (Ex.P-11), 20-10-1986 (Ex.P-12), 10-
12-1986(Ex.P-13),  10-02-1987  (Ex.P-14),  11-04-
1987(Ex.P-16),  10-08-1987(Ex.P-17)  and  10-10-1987  
(Ex.P-18) calling upon defendant no.1 to give an offer of  
deposit of balance 25% of the premium so as to bring the  
total payment equivalent to 50% of the total premium  
and  for  release  of  the  possession  of  the  land  to  the  
plaintiff  for  purpose  of  construction.   Defendant  no.1  
vide  its  letter  received  on  1.12.1987  by  the  plaintiff  
(Ex.P-19) sought the consent of the plaintiff to abide by  
the recommendations of the high-powered committee and  
the consent was duly given on the even date (Ex.P-20).  
Thereafter no offer was made to the plaintiff and without  
any  notice  of  compliance  for  payment,  the  letter  of  
cancellation dated 6.10.1993 (Ex.P-26) was issued.  It  
appears that defendant no.1 itself was not aware of the  
land being non-Nazul land as the first communication  
was addressed to the plaintiff only on 1.3.1990. 
68. The present case is one where defendant no.1 has  
not even suffered a loss.  The plot was to be purchased by 
the plaintiff at Rs.3.12 crores and it was finally sold to a  
third party at Rs.11.78 crores, i.e. almost three and a half 
times  the  price.   During  this  period  defendant  no.1  
continued to enjoy the earnest money of the plaintiff of  
Rs.78.00 lacs.
69. In  view  of  the  prolonged  period,  exchange  of  
communications, the plaintiff making various offers but  
not  complying  with  the  initial  terms,  defendant  no.1  
taking its own time in the decision making process, I am  
of the considered view that the plaintiff is entitled to the  
refund  of  the  earnest  money  of  Rs.78.00  lacs  but  no  
further amount is liable to be paid to the plaintiff.” 
11

Source PDF page 12

Open this page in the original PDF
Page  12
12. DDA  appealed  against  the  Single  Judge’s  judgment  to  a  
Division Bench of the Delhi High Court.  The Division Bench set  
aside the judgment of the Single Judge holding that the forfeiture of  
the earnest money by the DDA was in order. 
13. Shri Paras Kuhad, learned Senior Advocate appearing on behalf  
of the appellant, urged that time may have been of the essence under  
the original terms and conditions of the auction.  However, time had  
been extended on several occasions and, therefore, ceased to be of the  
essence.   In  answer  to  the  letter  dated  1.12.1987,  the  appellant  
promptly replied and said it would be willing to pay the entire 75%  
with 18% interest and, therefore, there was no breach of contract on  
the part of the appellant. Further, since the DDA sold the plot for  
11.78 Crores (Rupees Eleven Crores Seventy Eight Lakhs), there was  
no loss caused to the DDA and, hence forfeiture of earnest money  
would not be in accordance with the agreement or in accordance with  
law. 
14. Shri Amarendra Sharan, learned Senior Advocate appearing on  
behalf of the DDA, rebutted these contentions and added that the case  
was covered by the judgment in  Shree Hanuman Cotton Mills &  
12

Source PDF page 13

Open this page in the original PDF
Page  13
Anr. v. Tata Aircraft Ltd., 1970 (3) SCR 127.     He argued further  
that since the letter of 1.12.1987 had been issued under a mistake of  
fact, it would be void under Section 20 of the Contract Act and the  
said letter should, therefore, be ignored.    If it is ignored, then the  
termination of the contract and the forfeiture of earnest money are  
completely in order as the appellant was in breach.    The fact that the  
DDA ultimately sold the plot for a much larger sum, according to  
learned counsel, would be irrelevant inasmuch as the contractual term  
agreed  upon  between  parties  would  entitle  him  to  forfeit  earnest  
money on breach without any necessity of proving actual loss. 
15. Having heard learned counsel for the parties, it is important at  
the very outset to notice that earnest money can be forfeited under  
sub-clause (iv) set out hereinabove, only in the case of default, breach, 
or non-compliance of any of the terms and conditions of the auction,  
or on misrepresentation by the bidder. It may be noted that the balance 
75% which had to be paid within three months of the acceptance of  
the bid, was not insisted upon by the DDA.  On the contrary, after  
setting up two High Powered Committees which were instructed to  
look into the grievances of the appellant, the DDA extended time at  
13

Source PDF page 14

Open this page in the original PDF
Page  14
least twice. It is, therefore, very difficult to say that there was a breach  
of any terms and conditions of the auction, as the period of three  
months which the DDA could have insisted  upon had specifically  
been waived.  It is nobody’s case that there is any misrepresentation  
here by the bidder.  Therefore, under sub-clause (iv), without more,  
earnest money could not have been forfeited. 
16. The other noticeable feature of this case on facts is that DDA  
specifically requested the appellant to give their consent to make the  
balance payable along with 18% interest charges on belated payment.  
This  was  on  the  footing  that  the  Nazul  Rules  of  1981  would  be  
relaxed by the Central Government.  The reason why the letter is  
marked “without prejudice”  and the DDA made it clear that the letter  
does not  carry  any  commitment,  is obviously  because  the  Central  
Government may not relax the provision of the Nazul Rules, in which  
case nothing further could be done by the DDA.  If, however, the  
Central Government was willing to condone the delay, DDA would be 
willing  to  take  75%  of  the  outstanding  amount  along  with  18%  
interest. 
14

Source PDF page 15

Open this page in the original PDF
Page  15
17. Mr. Sharan argued that since the Central Government ultimately 
found that this was not a Nazul land, the letter was obviously based on 
a mistake of fact and would be void under Section 20 of the Contract  
Act.  We are afraid we are not able to accept this plea.  Long after the  
Central Government informed DDA (on 1.3.1990) that the property  
involved in the present case is not Nazul land, the DDA by its letter of  
6.10.1993 cancelled the allotment of the plot because the appellant  
had  failed  to  deposit  the  balance  75%.   DDA’s  understanding,  
therefore, was that what was important was payment of the balance  
75% which was insisted upon by the letter dated 1.12.1987 and which  
was acceded  to  by  the  respondent  immediately  on  the  same  date.  
Further,  Mr.  Sharan’s  argument  that  since  the  letter  was  “without 
prejudice” and since no commitment had been made, they were not  
bound by the terms of the letter also fails to impress us.  The letter  
was without prejudice and no commitment could have been given by  
the DDA because the Central Government may well not relax the  
Nazul Rules.  On the other hand, if the Central Government had, later  
on, relaxed the Nazul Rules, DDA could not be heard to say that  
despite this having been done, DDA would yet cancel the allotment of  
the plot.  That this could not have been done is clear because of the  
15

Source PDF page 16

Open this page in the original PDF
Page  16
aforesaid construction of the letter dated 1.12.1987 and also because  
DDA is a public authority bound by Article 14 and cannot behave  
arbitrarily. 
18. It  now  remains to  deal  with  the  impugned  judgment  of  the  
Division Bench. 
19. The  Division  Bench  followed  the  judgment  of  Tilley v. 
Thomas, (1867 3 Ch.A 61)  and distinguished the judgment in Webb 
v. Hughes, V .C.M. 1870.  It further went on to follow  Anandram 
Mangturam v. Bholaram Tanumal, ILR 1946 Bom 218 and held:
“The  decision  holds  that  the  principle  of  law  is  that  
where, by agreement, time is made of the essence of the  
contract, it cannot be waived by a unilateral act of a  
party and unless there is consensus ad-idem between the  
parties and a new date is agreed to, merely because a  
party  to  a  contract  agrees  to  consider  time  being  
extended for the opposite party to complete the contract,  
but ultimately refuses to accord concurrence would not  
mean  that  the  party  has  by  conduct  waived  the  date  
originally  agreed  as  being  of  the  essence  of  the  
contract.” (At para 32)
20. In our judgment, Webb’s case would directly apply to the facts  
here.  In that case, it was held:
  “ But if time be made the essence of the contract, that  
may be waived by the conduct of the purchaser; and if  
the time is once allowed to pass, and the parties go on  
negotiating for completion of the purchase, then time is  
16

Source PDF page 17

Open this page in the original PDF
Page  17
no longer of the essence of the contract.  But, on the  
other hand, it must be borne in mind that a purchaser is  
not bound to wait an indefinite time; and if he finds,  
while the negotiations are going on, that a long time will  
elapse before the contract can be completed, he may in a  
reasonable manner give notice to the vendor, and fix a  
period at which the business is to be terminated.” 
21. Based on the facts of this case, the Single Judge was correct in  
observing  that  the  letter  of  cancellation  dated  6.10.1993  and  
consequent forfeiture of earnest money was made without putting the  
appellant on notice that it has to deposit the balance 75% premium of  
the plot within a certain stated time.  In the absence of such notice,  
there  is  no  breach  of  contract  on  the  part  of  the  appellant  and  
consequently earnest money cannot be forfeited. 
22.    Tilley v. Thomas, (1867 3 Ch.A 61)  would not apply for the  
reason that the expression “without prejudice” was only used as stated  
above  because  the  Central  Government  may  not  relax  the  Nazul  
Rules. 
23. In Anandram Mangturam v. Bholaram Tanumal, ILR 1946  
Bom  218,  two  separate  judgments  were  delivered,  one   by  Chief  
Justice Stone and the other by Chagla,J. as he then was.  Stone C.J.  
held:-
17

Source PDF page 18

Open this page in the original PDF
Page  18
“In my judgment, reading the correspondence as a  
whole,  it  at  no  stage  passed  from  the  melting  pot  of  
negotiations to crystallize as an agreement to extend the  
time for the performance of the contract. The attitude of  
the  purchaser  throughout  the  correspondence  was:  
“Satisfy us that you are doing your best to obtain the  
goods  from  your  suppliers  and  we  will  then  consider 
fixing a new date for delivery of the goods to us”. On the  
other hand the attitude of the vendors throughout the  
correspondence  was  to  avoid  the  purchaser's  demand  
and  to  simply  say:  “You  know  that  we  cannot  effect  
delivery from our suppliers and until we do so we cannot  
deliver  the  goods  to  you”.  There  was  never  in  my  
judgment any consensus ad-idem, no agreement, express  
or implied, to extend the time either to any particular  
date  or  to  the  happening  of  some  future  event.  Mere  
forbearance in my opinion to institute proceedings or to  
give notice of rescission cannot be an extension of the  
time  for  the  performance  of  a  contract  within  the  
meaning of s. 63 of the Contract Act.” (at 226 & 227)
 Chagla, J. in a separate judgment held:-
“Under s. 55 of the Indian Contract Act, the promisee  
is  given  the  option  to  avoid  the  contract  where  the  
promisor fails to perform the contract at the time fixed in  
the contract. It is open to the promisee not to exercise the  
option or to exercise the option at any time, but it is clear  
to my mind that the promisee cannot by the mere fact of  
not  exercising  the  option  change  or  alter  the  date  of  
performance fixed under the contract itself. Under s. 63  
of  the  Indian  Contract  Act,  the  promisee  may  make  
certain  concessions  to  the  promisor  which  are  
advantageous to the promisor, and one of them is that he  
may extend the time for such performance. But it is clear  
again  that  such  an  extension  of  time  cannot  be  a  
unilateral extension on the part of the promisee. It is only  
at  the  request  of  the  promisor  that  the  promisee  may 
agree  to  extend  the  time  of  performance  and  thereby  
bring  about  an  agreement  for  extension  of  time.  
18

Source PDF page 19

Open this page in the original PDF
Page  19
Therefore it is only as a result of the operation of s. 63 of  
the Indian Contract Act that the time for the performance  
of the contract can be extended and that time can only be  
extended  by  an  agreement  arrived  at  between  the  
promisor and the promisee.” (at 229)
24. The  aforesaid  judgment  would  apply  in  a  situation  where  a 
promisee accedes to the request of the promisor to extend time that is  
fixed for his own benefit.  Thus, in Keshavlal Lallubhai Patel and  
Ors.  v.  Lalbhai  Trikumlal  Mills  Ltd 1959  SCR  213,  this  Court  
held:-
“The true legal position in regard to the extension of  
time  for the  performance  of  a  contract  is  quite  clear  
under s.  63 of the Indian Contract Act. Every promisee,  
as  the  section  provides,  may  extend  time  for  the  
performance  of  the  contract.  The  question  as  to  how  
extension of time may be agreed upon by the parties has  
been the subject-matter of some argument at the Bar in  
the present appeal. There can be no doubt, we think, that  
both the buyer and the seller must agree to extend time  
for the delivery of goods. It would not be open to the  
promisee  by  his  unilateral  act  to  extend  the  time  for  
performance of his own accord for his own benefit.”
25. However, such is not the position here.  In the present case, the  
appellant  is  the  promisor  and  DDA is  the  promisee.   In  such  a  
situation, DDA can certainly unilaterally extend the time for payment  
under Section 63 of the Contract Act as the time for payment is not for 
19

Source PDF page 20

Open this page in the original PDF
Page  20
DDA’s own benefit but for the benefit of the appellant.  The present  
case would be covered by two judgments of the Supreme Court. In  
Citi Bank N.A.  v.  Standard Chartered Bank,  (2004) 1 SCC Page  
12, this Court held:
“50. Under Section 63, unlike Section 62, a promisee  
can act unilaterally and may
(i) dispense with wholly or in part, or
(ii) remit wholly or in part,
the performance of the promise made to him, or
(iii) may extend the time for such performance, or
(iv) may accept instead of it any satisfaction which he  
thinks fit.”
26. Similarly in S. Brahmanand v. K.R. Muthugopal, (2005) 12 
SCC 764 the Supreme Court held:
“34. Thus,  this  was  a  situation  where  the  original  
agreement  of  10-3-1989  had  a  “fixed  date”  for  
performance, but by the subsequent letter of 18-6-1992  
the  defendants  made  a  request  for  postponing  the  
performance to a future date without fixing any further  
date for performance. This was accepted by the plaintiffs  
by  their  act  of  forbearance  and  not  insisting  on  
performance forthwith. There is nothing strange in time  
for performance being extended, even though originally  
the  agreement  had  a  fixed  date.  Section  63  of  the  
Contract  Act,  1872  provides  that  every  promisee  may 
extend time for the performance of the contract. Such an  
agreement  to  extend  time  need  not  necessarily  be  
reduced to writing, but may be proved by oral evidence  
20

Source PDF page 21

Open this page in the original PDF
Page  21
or, in some cases, even by evidence of conduct including  
forbearance on the part of the other party. [See in this  
connection the observations of this Court in  Keshavlal 
Lallubhai  Patel  v. Lalbhai  Trikumlal  Mills  Ltd. ,  1959  
SCR 213 : AIR 1958 SC 512, para 8. See also in this  
connection Saraswathamma v. H.  Sharad  Shrikhande , 
AIR  2005  Kant  292  and  K.  Venkoji  Rao  v. M.  Abdul  
Khuddur  Kureshi,  AIR  1991  Kant  119,  following  the  
judgment in Keshavlal Lallubhai Patel (supra).] Thus, in  
this  case  there  was  a  variation  in  the  date  of  
performance by express representation by the defendants, 
agreed to by the act of forbearance on the part of the  
plaintiffs. What was originally covered by the first part of  
Article 54, now fell within the purview of the second part  
of  the  article.  Pazhaniappa  Chettiyar  v. South  Indian  
Planting and Industrial Co. Ltd. [AIR 1953 Trav Co 161] 
was a similar instance where the contract when initially  
made  had  a  date  fixed  for  the  performance  of  the  
contract but the Court was of the view that “in the events  
that happened in this case, the agreement in question  
though  started  with  fixation  of  a  period  for  the  
completion of the transaction became one without such  
period  on  account  of  the  peculiar  facts  and  
circumstances  already  explained  and  the  contract,  
therefore, became one in which no time was fixed for its  
performance” and held that what was originally covered  
by the first part of Article 113 of the Limitation Act, 1908  
would  fall  under  the  second  part  of  the  said  article  
because  of  the  supervening  circumstances  of  the  
case.”(at Page 777)
27. Coming to the application of Article 14, the Division Bench in  
paragraph 37 stated:-
“37. Now, in India, reasonableness in State action is a  
facet of Article 14 of the Constitution of India and in the  
field of contract would have a considerable play at the  
precontract  stage.  Once  parties  have  entered  into  a  
21

Source PDF page 22

Open this page in the original PDF
Page  22
contractual  obligation,  they  would  be  bound  by  the  
contract and the only reasonableness would be of the  
kind  envisaged  by  the  Supreme  Court  in  the  decision  
reported  as  AIR  1963  SC  1144  T.P .  Daver  v.  Lodge 
Victoria No.363 SC Belgaum & Ors. On the subject of a  
member of a club being expelled, and the relationship  
being a contract as per the rules and regulations of the  
club,  adherence  whereto  was  agreed  to  by  he  who  
became a member of the club and the management of the  
club, the Supreme Court observed that in such private  
affairs, it would be good faith in taking an action which  
is rooted in the minds of modern men and women i.e. in a  
modern democratic society and no more. The decision  
guides that where a private affair i.e. a contract is so  
perverted by a party that it offends the concept of a fair-
play in a modern society, alone then can the action be  
questioned as not in good faith and suffice would it be to  
state  that  anything  done  not  in  good  faith  would  be  
unreasonably done.”
28. It will be noticed at once that T.P. Daver v. Lodge Victoria No. 
363, S.C. Belgaum, 1964 (1) SCR 1, is not an authority on Article 14  
at all.  It deals with clubs and the fact that rules or bye-laws which  
bind members of such clubs have to be strictly adhered to.  On the  
other hand in ABL International Ltd.  v. Export Credit Guarantee  
Corpn. of India Ltd.,  (2004) 3 SCC 553 at paras 22 and 23, the  
Supreme Court held:
“22. We  do  not  think  the  above  judgment  in  VST 
Industries Ltd.  [(2001) 1 SCC 298 : 2001 SCC (L&S)  
227] supports the argument of the learned counsel on the  
question of maintainability of the present writ petition. It  
is  to  be  noted  that VST Industries  Ltd. [(2001)  1  SCC 
22

Source PDF page 23

Open this page in the original PDF
Page  23
298  :  2001  SCC  (L&S)  227]  against  whom  the  writ  
petition was filed was not a State or an instrumentality of  
a  State  as  contemplated  under  Article  12  of  the  
Constitution, hence, in the normal course, no writ could  
have been issued against the said industry. But it was the  
contention of the writ petitioner in that case that the said  
industry was obligated under the statute concerned to  
perform certain public functions; failure to do so would  
give  rise  to  a  complaint  under  Article  226  against  a  
private  body.  While  considering  such  argument,  this  
Court  held  that  when  an  authority  has  to  perform  a  
public function or a public duty, if there is a failure a  
writ  petition  under  Article  226  of  the  Constitution  is  
maintainable. In the instant case, as to the fact that the  
respondent is an instrumentality of a State, there is no  
dispute  but  the  question  is:  was  the  first  respondent  
discharging  a  public  duty  or  a  public  function  while  
repudiating the claim of the appellants arising out of a  
contract?  Answer  to  this  question,  in  our  opinion,  is  
found in the judgment of this Court in the case of  Kumari 
Shrilekha Vidyarthi v. State of U.P . [(1991) 1 SCC 212 :  
1991 SCC (L&S) 742] wherein this Court held: (SCC pp.  
236-37, paras 22 & 24)
“The impact of every State action is also on  
public interest. … It is really the nature of its  
personality as State which is significant and  
must characterize all its actions, in whatever  
field,  and  not  the  nature  of  function,  
contractual or otherwise, which is decisive of  
the nature of scrutiny permitted for examining  
the  validity  of  its  act.  The  requirement  of  
Article 14 being the duty to act fairly, justly  
and  reasonably,  there  is  nothing  which  
militates against the concept of requiring the  
State  always  to  so  act,  even  in  contractual  
matters.”
23. It is clear from the above observations of this Court,  
once  the State or an instrumentality  of the  State is a  
party of the contract, it has an obligation in law to act  
23

Source PDF page 24

Open this page in the original PDF
Page  24
fairly, justly and reasonably which is the requirement of  
Article 14 of the Constitution of India. Therefore, if by  
the impugned repudiation of the claim of the appellants  
the first respondent as an instrumentality of the State has  
acted in contravention of the abovesaid requirement of  
Article 14, then we have no hesitation in holding that a  
writ court can issue suitable directions to set right the  
arbitrary actions of the first respondent.” 
29. Based on the facts of this case, it would be arbitrary for the  
DDA to forfeit the earnest money on two fundamental grounds.  First,  
there is no breach of contract on the part of the appellant as has been  
held above. And second, DDA not having been put to any loss, even if 
DDA could insist on a contractual stipulation in its favour, it would be  
arbitrary  to  allow  DDA  as  a  public  authority  to  appropriate  
Rs.78,00,000/- (Rupees Seventy Eight Lakhs) without any loss being  
caused. It is clear, therefore, that Article 14 would apply in the field of 
contract in this case and the finding of the Division Bench on this  
aspect is hereby reversed. 
30. We now come to the reasoning which involves Section 74 of  
the Contract Act.  The Division Bench held:
“38. The learned Single Judge has held that the property  
was ultimately  auctioned  in  the  year 1994  at  a  price  
which fetched DDA a handsome return of Rupees 11.78  
crores and there being no damages suffered by DDA, it  
could not forfeit the earnest money.
24

Source PDF page 25

Open this page in the original PDF
Page  25
 
39. The said view runs in the teeth of the decision of the  
Supreme  Court  reported  as  AIR  1970  SC  1986  Shree 
Hanuman Cotton Mills & Anr. V . Tata Aircraft Ltd. which 
holds  that  as  against  an  amount  tendered  by  way  of  
security,  amount  tendered  as  earnest  money  could  be  
forfeited as per terms of the contract. 
40. We may additionally observe that original time to pay 
the balance bid consideration, as per Ex.P-I was May  
18, 1982 and as extended by Ex. P-8 was October 28,  
1982. That DDA could auction the plot in the year 1994  
in the sum of Rupees 11.78 crore was immaterial and not  
relevant evidence for the reason damages with respect to  
the price of property have to be computed with reference  
to the date of the breach of the contract.”
31. Section 74 as it originally stood read thus:
“When a contract has been broken, if a sum is named in  
the contract as the amount to be paid in case of such  
breach, the party complaining of the breach is entitled,  
whether or not actual damage or loss is proved to have  
been caused thereby, to receive from the party who has  
broken  the  contract  reasonable  compensation  not  
exceeding the amount so named.”
32. By an amendment made in 1899, the Section was amended to  
read:
“74. Compensation for breach of contract where penalty  
stipulated for.— When a contract has been broken, if a  
sum is named in the contract as the amount to be paid in  
case of such breach, or if the contract contains any other  
stipulation by way of penalty, the party complaining of  
the breach is entitled, whether or not actual damage or  
loss is proved to have been caused thereby, to receive  
from the party who has broken the contract reasonable  
25

Source PDF page 26

Open this page in the original PDF
Page  26
compensation not exceeding the amount so named or, as  
the case may be, the penalty stipulated for.
Explanation.—A stipulation for increased interest from  
the  date  of  default  may  be  a  stipulation  by  way  of  
penalty.
Exception.—When any person enters into any bail-bond,  
recognizance or other instrument of the same nature, or,  
under the provisions of any law, or under the orders of  
the  Central  Government  or  of  any  State  Government,  
gives any bond for the performance of any public duty or  
act in which the public are interested, he shall be liable,  
upon breach of any condition of any such instrument, to  
pay the whole sum mentioned therein.
Explanation.—A person who enters into a contract with  
Government does not necessarily thereby undertake any  
public duty, or promise to do an act in which the public  
are interested.”
33. Section 74 occurs in Chapter 6 of the Indian Contract Act, 1872  
which reads “Of the consequences of breach of contract”. It is in fact  
sandwiched  between  Sections  73  and  75  which  deal  with  
compensation for loss or damage caused by breach of contract and  
compensation for damage which a party may sustain through non-
fulfillment  of  a  contract  after  such  party  rightfully  rescinds  such  
contract.    It  is  important  to  note  that  like  Sections  73  and  75,  
compensation is payable for breach of contract under Section 74 only  
where damage or loss is caused by such breach. 
26

Source PDF page 27

Open this page in the original PDF
Page  27
34. In Fateh Chand v.  Balkishan Das,  1964 SCR (1) 515,  this  
Court held:
“The  section  is  clearly  an  attempt  to  eliminate  the  
somewhat elaborate refinements made under the English  
common  law  in  distinguishing  between  stipulations  
providing  for  payment  of  liquidated  damages  and  
stipulations in the nature of penalty. Under the common  
law  a  genuine  pre-estimate  of  damages  by  mutual  
agreement is regarded as a stipulation naming liquidated  
damages and binding between the parties: a stipulation  
in  a  contract  in  terrorem  is  a  penalty  and  the  Court 
refuses to enforce it, awarding to the aggrieved party  
only  reasonable  compensation.  The  Indian  Legislature 
has  sought  to  cut  across  the  web  of  rules  and  
presumptions  under  the  English  common  law,  by  
enacting  a  uniform  principle  applicable  to  all  
stipulations  naming  amounts  to  be  paid  in  case  of  
breach, and stipulations by way of penalty.
….
   Section 74 of the Indian Contract Act deals with the  
measure of damages in two classes of cases (i) where the  
contract names a sum to be paid in case of breach and  
(ii) where the contract contains any other stipulation by  
way of penalty. We are in the present case not concerned  
to decide whether a covenant of forfeiture of deposit for  
due performance of a contract falls within the first class.  
The  measure  of  damages  in  the  case  of  breach  of  a  
stipulation by way of penalty is by Section  74 reasonable 
compensation not exceeding the penalty stipulated for. In  
assessing damages the Court has, subject to the limit of  
the  penalty  stipulated,  jurisdiction  to  award  such  
compensation as it deems reasonable having regard to  
all  the  circumstances  of  the  case.  Jurisdiction  of  the  
Court  to  award  compensation  in  case  of  breach  of  
contract  is  unqualified  except  as  to  the  maximum  
stipulated; but compensation has to be reasonable, and  
that imposes upon the Court duty to award compensation  
27

Source PDF page 28

Open this page in the original PDF
Page  28
according to settled principles. The section undoubtedly  
says  that  the  aggrieved  party  is  entitled  to  receive  
compensation  from  the  party  who  has  broken  the  
contract, whether or not actual damage or loss is proved  
to have been caused by the breach. Thereby it merely  
dispenses with proof of "actual loss or damages"; it does  
not  justify  the  award  of  compensation  when  in  
consequence  of  the  breach  no  legal  injury  at  all  has  
resulted, because compensation for breach of contract  
can be  awarded  to make  good loss or damage  which  
naturally arose in the usual course of things, or which  
the  parties  knew  when  they  made  the  contract,  to  be  
likely to result from the breach.”(At page 526, 527)
   Section 74 declares the law as to liability upon breach  
of contract where compensation is by agreement of the  
parties pre-determined, or where there is a stipulation by  
way of penalty. But the application of the enactment is  
not restricted to cases where the aggrieved party claims  
relief as a plaintiff. The section does not confer a special  
benefit upon any party; it merely declares the law that  
notwithstanding any term in the contract predetermining  
damages or providing for forfeiture of any property by  
way  of  penalty,  the  court  will  award  to  the  party  
aggrieved only reasonable compensation not exceeding  
the amount named or penalty stipulated. The jurisdiction  
of  the  court  is  not  determined  by  the  accidental  
circumstance of the party in default being a plaintiff or a  
defendant in a suit. Use of the expression "to receive  
from the party who has broken the contract" does not  
predicate  that  the  jurisdiction  of  the  court  to  adjust  
amounts which have been paid by the party in default  
cannot be exercised in dealing with the claim of the party  
complaining  of  breach  of  contract.  The  court  has  to  
adjudge in every case reasonable compensation to which  
the plaintiff is entitled from the defendant on breach of  
the contract. Such compensation has to be ascertained  
having regard to the conditions existing on the date of  
the breach.”(At page 530)
28

Source PDF page 29

Open this page in the original PDF
Page  29
35. Similarly, in  Maula Bux v. Union of India (UOI),  1970 (1)  
SCR 928, it was held:
     “Forfeiture of earnest money under a contract for  
sale of property-movable or immovable-if the amount is  
reasonable,  does  not  fall  within  Section  74.  That  has  
been decided in several cases :Kunwar Chiranjit Singh v.  
Har Swarup,  A.I.R.1926 P .C.1; Roshan Lal v. The Delhi  
Cloth  and  General  Mills  Company  Ltd.,  Delhi,  I.L.R. 
All.166; Muhammad  Habibullah  v.  Muhammad  
Shafi, I.L.R.  All.  324; Bishan  Chand  v.  Radha  Kishan  
Das, I.D. 19 All. 49. These cases are easily explained, for  
forfeiture of a reasonable amount paid as earnest money  
does not amount to imposing a penalty. But if forfeiture is 
of the nature of penalty, Section  74 applies. Where under  
the  terms  of  the  contract  the  party  in  breach  has  
undertaken to pay a sum of money or to forfeit a sum of  
money  which  he  has  already  paid  to  the  party  
complaining of a breach of contract, the undertaking is  
of the nature of a penalty.
Counsel for the Union, however, urged that in the present 
case Rs. 10,000/- in respect of the potato contract and  
Rs. 8,500 in respect of the poultry contract were genuine  
pre-estimates of damages which the Union was likely to  
suffer as a result of breach of contract, and the plaintiff  
was not entitled to any relief against forfeiture. Reliance  
in  support  of  this  contention  was  placed  upon  the  
expression (used in Section  74 of the Contract Act), "the  
party complaining of the breach is entitled, whether or  
not actual damage or loss is proved to have been caused  
thereby, to receive from the party who has broken the  
contract  reasonable  compensation".  It  is  true  that  in  
every case of breach of contract the person aggrieved by  
the breach is not required to prove actual loss or damage  
suffered by him before he can claim a decree, and the  
Court is competent to award reasonable compensation in  
case of breach even if no actual damage is proved to  
have  been  suffered  in  consequence  of  the  breach  of  
29

Source PDF page 30

Open this page in the original PDF
Page  30
contract.  But  the  expression  "whether  or  not  actual  
damage or loss is proved to have been caused thereby" is  
intended  to  cover  different  classes  of  contracts  which  
come  before  the  Courts.  In  case  of  breach  of  some  
contracts it may be impossible for the Court to assess  
compensation arising from breach, while in other cases  
compensation  can  be  calculated  in  accordance  with  
established rules. Where the Court is unable to assess the  
compensation,  the  sum  named  by  the  parties  if  it  be  
regarded as a genuine pre-estimate may be taken into  
consideration  as  the  measure  of  reasonable  
compensation, but not if the sum named is in the nature  
of  a  penalty.  Where  loss  in  terms  of  money  can  be  
determined, the party claiming compensation must prove  
the loss suffered by him.
In the present case, it was possible for the Government of  
India  to  lead  evidence  to  prove  the  rates  at  which  
potatoes, poultry, eggs and fish were purchased by them  
when the plaintiff failed to deliver "regularly and fully"  
the quantities stipulated under the terms of the contracts  
and after the contracts were terminated. They could have  
proved the rates at which they had to be purchased and  
also  the other incidental charges incurred  by them in  
procuring the goods contracted for. But no such attempt  
was made.”(At page 933,934)
36. In  Shree Hanuman Cotton Mills and Anr. v. Tata Aircraft  
Limited, 1970 (3) SCR 127 it was held:
“From  a  review  of  the  decisions  cited  above,  the  
following principles emerge regarding "earnest":
(1) It must be given at the moment at which the contract  
is concluded.
30

Source PDF page 31

Open this page in the original PDF
Page  31
(2) It represents a guarantee that the contract will be  
fulfilled or, in other words, 'earnest' is given to bind the  
contract.
(3) It is part of the purchase price when the transaction  
is carried out.
(4) It is forfeited when the transaction falls through by  
reason of the default or failure of the purchaser.
(5) Unless there is anything to the contrary in the terms  
of the contract, on default committed by the buyer, the  
seller is entitled to forfeit the earnest” (At page 139) 
“The learned Attorney General very strongly urged that  
the  pleas  covered  by  the  second  contention  of  the  
appellant had never been raised in the pleadings nor in  
the  contentions  urged  before  the  High  Court.  The  
question of the quantum of earnest deposit which was  
forfeited being unreasonable or the forfeiture being by  
way of penalty, were never raised by the appellants. The  
Attorney General also pointed out that as noted by the  
High Court the appellants led no evidence at all and,  
after abandoning the various pleas taken in the plaint,  
the only question pressed before the High Court was that  
the deposit was not by way of earnest and hence the  
amount could not be forfeited. Unless the appellants had  
pleaded and established that there was unreasonableness  
attached to the amount required to be deposited under  
the  contract  or  that  the  clause  regarding  forfeiture  
amounted  to  a  stipulation  by  way  of  a  penalty,  the  
respondents had no opportunity to satisfy the Court that  
no question of unreasonableness or the stipulation being  
by  way  of  penalty  arises.  He  further  urged  that  the  
question  of  unreasonableness  or  otherwise  regarding  
earnest money does not at all arise when it is forfeited  
according to the terms of the contract.
    In our opinion the learned Attorney General is well  
founded in his contention that the appellants raised no  
31

Source PDF page 32

Open this page in the original PDF
Page  32
such  contentions  covered  by  the  second  point,  noted  
above. It is therefore unnecessary for us to go into the  
question  as  to  whether  the  amount  deposited  by  the  
appellants, in this case, by way of earnest and forfeited  
as such, can be considered to be reasonable or not. We  
express no opinion on the question  as to whether the  
element  of  unreasonableness  can  ever  be  considered  
regarding the forfeiture of an amount deposited by way  
of earnest and if so what are the necessary factors to be  
taken into account in considering the reasonableness or  
otherwise of the amount deposited by way of earnest. If  
the  appellants were  contesting the  claim  on any  such  
grounds, they should  have laid the foundation for the  
same by raising appropriate pleas and also led proper  
evidence  regarding  the  same,  so  that  the  respondents  
would  have  had  an  opportunity  of  meeting  such  a  
claim.”(At page 142)
37. And finally in ONGC Ltd.  v. Saw Pipes Ltd. , (2003) 5 SCC  
705, it was held:
“64. It is apparent from the aforesaid reasoning recorded 
by the Arbitral Tribunal that it failed to consider Sections 
73 and 74 of the Indian Contract Act and the ratio laid  
down in Fateh Chand case  [AIR 1963 SC 140: (1964) 1  
SCR 515 at p. 526] wherein it is specifically held that  
jurisdiction of the court to award compensation in case  
of  breach  of  contract  is  unqualified  except  as  to  the  
maximum  stipulated;  and  compensation  has  to  be  
reasonable. Under Section 73, when a contract has been  
broken, the party who suffers by such breach is entitled  
to receive compensation for any loss caused to him which 
the parties knew when they made the contract to be likely  
to result from the breach of it. This section is to be read  
with Section 74, which deals with penalty stipulated in  
the  contract, inter  alia (relevant  for  the  present  case)  
provides that when a contract has been broken, if a sum  
32

Source PDF page 33

Open this page in the original PDF
Page  33
is named in the contract as the amount to be paid in case  
of  such  breach,  the  party  complaining  of  breach  is  
entitled, whether or not actual loss is proved to have  
been caused, thereby to receive from the party who has  
broken  the  contract  reasonable  compensation  not  
exceeding the amount so named. Section 74 emphasizes  
that in case of breach of contract, the party complaining  
of  the  breach  is  entitled  to  receive  reasonable  
compensation whether or not actual loss is proved to  
have  been  caused  by  such  breach.  Therefore,  the  
emphasis  is  on  reasonable  compensation.  If  the  
compensation named in the contract is by way of penalty,  
consideration would be different and the party is only  
entitled to reasonable compensation for the loss suffered.  
But if the compensation named in the contract for such  
breach is genuine pre-estimate of loss which the parties  
knew when they made the contract to be likely to result  
from the breach of it, there is no question of proving such 
loss or such party is not required to lead evidence to  
prove actual loss suffered by him.
67……..In  our  view,  in  such  a  contract,  it  would  be  
difficult to prove exact loss or damage which the parties  
suffer because of the breach thereof. In such a situation,  
if the parties have pre-estimated such loss after clear  
understanding, it would be totally unjustified to arrive at  
the conclusion that the party who has committed breach  
of  the  contract  is  not  liable  to  pay  compensation.  It  
would be against the specific provisions of Sections 73  
and 74 of the Indian Contract Act. There was nothing on  
record  that  compensation  contemplated  by  the  parties 
was in any way unreasonable. It has been specifically  
mentioned that it was an agreed genuine pre-estimate of  
damages  duly  agreed  by  the  parties.  It  was  also  
mentioned that the liquidated damages are not by way of  
penalty. It was also provided in the contract that such  
damages are to be recovered by the purchaser from the  
bills for payment of the cost of material submitted by the  
contractor.  No  evidence  is  led  by  the  claimant  to  
establish  that  the  stipulated  condition  was  by  way  of  
33

Source PDF page 34

Open this page in the original PDF
Page  34
penalty or the compensation contemplated was, in any  
way, unreasonable. There was no reason for the Tribunal  
not to rely  upon the clear and unambiguous terms of  
agreement stipulating pre-estimate damages because of  
delay in supply of goods. Further, while extending the  
time  for  delivery  of  the  goods,  the  respondent  was  
informed  that  it  would  be  required  to  pay  stipulated  
damages.
68. From the aforesaid discussions, it can be held that:
(1) Terms of the contract are required to be taken into  
consideration before arriving at the conclusion whether  
the party claiming damages is entitled to the same.
(2) If the terms are clear and unambiguous stipulating  
the  liquidated  damages  in  case  of  the  breach  of  the  
contract  unless  it  is  held  that  such  estimate  of  
damages/compensation is unreasonable or is by way of  
penalty, party who has committed the breach is required  
to pay such compensation and that is what is provided in  
Section 73 of the Contract Act.
(3) Section 74 is to be read along with Section 73 and,  
therefore, in every case of breach of contract, the person  
aggrieved by the breach is not required to prove actual  
loss or damage suffered by him before he can claim a  
decree.  The  court  is  competent  to  award  reasonable  
compensation in case of breach even if no actual damage  
is proved to have been suffered in consequence of the  
breach of a contract.
(4) In  some  contracts,  it would  be  impossible  for the  
court  to  assess  the  compensation  arising  from  breach 
and if the compensation contemplated is not by way of  
penalty or unreasonable, the court can award the same if  
it is genuine pre-estimate by the parties as the measure of 
reasonable compensation.”
34

Source PDF page 35

Open this page in the original PDF
Page  35
38. It  will  be  seen  that  when  it  comes  to  forfeiture  of  earnest  
money, in Fateh Chand’s case, counsel for the appellant conceded on  
facts that Rs.1,000/- deposited as earnest money could be forfeited.  
(See: 1964 (1) SCR Page 515 at 525 and 531). 
39. Shree  Hanuman  Cotton  Mills  &  Another  which  was  so  
heavily relied by the Division  Bench again  was a  case  where  the  
appellants conceded that they committed breach of contract.  Further,  
the respondents also pleaded that the appellants had to pay them a sum 
of Rs.42,499/- for loss and damage sustained by them. (See: 1970 (3)  
SCR  127  at  Page  132).   This  being  the  fact  situation,  only  two  
questions were argued before the Supreme Court: (1) that the amount  
paid by the plaintiff is not earnest money and (2) that forfeiture of  
earnest  money  can  be  legal  only  if  the  amount  is  considered  
reasonable. (at page 133). Both questions were answered against the  
appellant. In deciding question two against the appellant, this Court  
held:-
“But, as we have already mentioned, we do not propose  
to  go  into  those  aspects  in  the  case  on  hand.  As  
mentioned  earlier,  the  appellants  never  raised  any  
contention that the forfeiture of the amount amounted to  
a penalty or that the amount forfeited is so large that the  
forfeiture  is  bad  in  law.  Nor  have  they  raised  any  
35

Source PDF page 36

Open this page in the original PDF
Page  36
contention that the amount of deposit is so unreasonable  
and  therefore  forfeiture  of  the  entire  amount  is  not  
justified. The decision in Maula Bux's [1970]1SCR928  
had  no  occasion  to  consider  the  question  of  
reasonableness or otherwise of the earnest deposit being  
forfeited. Because, from the said judgment it is clear that  
this Court did not agree with the view of the High Court  
that  the  deposits  made,  and  which  were  under  
consideration, were paid as earnest money. It is under  
those  circumstances  that  this  Court  proceeded  to  
consider the applicability of Section  74 of the Contract  
Act. (At page 143)”
40. From the above, it is clear that this  Court held that  Maula 
Bux’s case was not, on facts, a case that related to earnest money.  
Consequently, the observation in Maula Bux that forfeiture of earnest 
money under a contract if reasonable does not fall within Section 74,  
and would fall within Section 74 only if earnest money is considered a 
penalty is not on a matter that directly arose for decision in that case.  
The law laid down by a Bench of 5 Judges in Fateh Chand’s case is  
that  all  stipulations naming  amounts to be paid in case  of  breach  
would be covered by Section 74. This is because Section 74  cuts  
across the rules of the English Common Law by enacting a uniform 
principle that would apply to all amounts to be paid in case of breach,  
whether they are in the nature of penalty or otherwise.  It must not be  
36

Source PDF page 37

Open this page in the original PDF
Page  37
forgotten that as has been stated above, forfeiture of earnest money on  
the facts in Fateh Chand’s case was conceded.  In the circumstances,  
it would therefore be correct to say that as earnest money is an amount 
to be paid in case of breach of contract and named in the contract as  
such, it would necessarily be covered by Section 74.
41. It must, however, be pointed out that in cases where a public  
auction  is  held,  forfeiture  of  earnest  money  may  take  place  even  
before an agreement is reached, as DDA is to accept the bid only after  
the earnest money is paid.  In the present case, under the terms and  
conditions  of  auction,  the  highest  bid  (along  with  which  earnest  
money has to be paid) may well have been rejected.   In such cases,  
Section  74  may  not  be  attracted  on  its  plain  language  because  it  
applies only “when a contract has been broken”.  
42. In the present case, forfeiture of earnest money took place long  
after an agreement had been reached.  It is obvious that the amount  
sought to be forfeited on the facts of the present case is sought to be  
forfeited without any loss being shown.  In fact it has been shown that  
far from suffering any loss, DDA has received a much higher amount  
on re-auction of the same plot of land.
37

Source PDF page 38

Open this page in the original PDF
Page  38
43. On  a  conspectus  of  the  above  authorities,  the  law  on  
compensation for breach of contract under Section 74 can be stated to  
be as follows:-
1. Where a sum is named in a contract as a liquidated amount  
payable  by  way  of  damages,  the  party  complaining  of  a 
breach  can  receive  as  reasonable  compensation  such  
liquidated  amount  only  if  it  is a  genuine  pre-estimate  of  
damages fixed by both parties and found to be such by the  
Court. In other cases, where a sum is named in a contract as  
a  liquidated  amount  payable  by  way  of  damages,  only  
reasonable compensation can be awarded not exceeding the  
amount so stated. Similarly, in cases where the amount fixed  
is in the nature of penalty, only reasonable compensation can 
be awarded not exceeding the penalty so stated.  In both  
cases, the liquidated amount or penalty is the upper limit  
beyond  which  the  Court  cannot  grant  reasonable  
compensation.
2. Reasonable  compensation  will  be  fixed  on  well  known  
principles that are applicable to the law of contract, which  
are to be found inter alia in Section 73 of the Contract Act. 
38

Source PDF page 39

Open this page in the original PDF
Page  39
3. Since  Section  74  awards  reasonable  compensation  for  
damage or loss caused by a breach of contract, damage or  
loss caused is a  sine qua non  for the applicability of the  
Section. 
4. The  Section  applies  whether  a  person  is  a  plaintiff  or  a  
defendant in a suit. 
5. The sum spoken of may already be paid or be payable in  
future. 
6. The expression “whether or not actual damage or loss is  
proved to have been caused thereby” means that where it is  
possible to prove actual damage or loss, such proof is not  
dispensed with.  It is only in cases where damage or loss is  
difficult or impossible to prove that the liquidated amount  
named in the contract, if a genuine pre-estimate of damage  
or loss, can be awarded. 
7. Section 74 will apply to cases of forfeiture of earnest money  
under  a  contract.  Where,  however,  forfeiture  takes  place 
under the terms and conditions of a public auction  before 
agreement is reached, Section 74 would have no application.
39

Source PDF page 40

Open this page in the original PDF
Page  40
44. The Division Bench has gone wrong in principle.  As has been  
pointed  out  above,  there  has  been  no  breach  of  contract  by  the  
appellant. Further, we cannot accept the view of the Division Bench  
that the fact that the DDA made a profit from re-auction is irrelevant,  
as that would fly in the face of the most basic principle on the award  
of  damages  –  namely,  that  compensation  can  only  be  given  for  
damage or loss suffered.  If damage or loss is not suffered, the law  
does not provide for a windfall. 
45. A great deal of the argument before us turned on notings in files 
that were produced during cross-examination of various witnesses.  
We have not referred to any of these notings and, consequently, to any 
case  law  cited  by  both  parties  as  we  find  it  unnecessary  for  the  
decision of this case. 
46. Mr. Sharan submitted that in case we were against him, the  
earnest money that should be refunded should only be refunded with  
7% per annum and not 9% per annum interest as was done in other  
cases.  We are afraid we are not able to agree as others were offered  
the refund of earnest money way back in 1989 with 7% per annum  
interest which they accepted. The DDA having chosen to fight the  
40

Source PDF page 41

Open this page in the original PDF
Page  41
present appellant tooth and nail even on refund of earnest money,  
when there was no breach of contract or loss caused to it, stands on a  
different footing. We, therefore, turn down this plea as well. 
47. In the result, the appeal is allowed.  The judgment and order of  
the Single Judge is restored.  Parties will bear their own costs. 
…..…………………J.
(Ranjan Gogoi)
…..…………………J.
(R.F. Nariman)
New Delhi;
January 09, 2015.
41